How to well prepare for your C2010-555 exam? You can now get IBM C2010-555 exam certification our CertTree have the full version of IBM C2010-555 exam. You do not need to look around for the latest IBM Maximo 7.6 C2010-555 questions and answers, because you have to find the best IBM Maximo 7.6 C2010-555 questions and answers. Rest assured that our IBM Maximo 7.6 C2010-555 questions and answers, you will be completely ready for the IBM C2010-555 certification exam.
Share some IBM Certified Deployment Professional C2010-555 exam questions and answers below.
A vendor requires a payment of 20% of the purchase price when the purchase order (PO) is sent and the company wants to withhold of the payment until 90 days after receiving the item before final payment is made.
How would this be accomplished'?
A. A Purchase Requisition would be created and three invoices would) be generated via the invoicing application One invoice tor 20%. one for 60% and one for 20%
B. A Price Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt.
C. A Blanket Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt
D. A Purchase Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt
Answer: D

A company has a requirement to report on actual labor hours, materials, services and tools used as work progresses on a work order. What is the earliest point in the basic life cycle a user can start reporting?
A.APPR
B. COMP
C. WMATL
D. WAPPR
Answer: A

A company wishes to group its location records into a hierarchy to assist users in searching for asset s.
How can this be accomplished?
A. Location Groups can be created and LIVE locations added
B. Locations can be linked by using the Related Records tab in the Locations application.
C. Location records will need to be added to a network and can only include locations with an ACTIVE status.
D. Location records need to be added a system and can only include locations with an OPERATING type.
Answer: D

A user belongs to two non-independent security groups, Group A and Group B Group A has a purchasing limit of 37000 and Group B has a purchasing limit of $8000.
What is the purchasing limit of a user who belongs to both security groups?
A. $7000
B. $8000
C. $15000
D. $56000
Answer: B

A company is training on the use of the material status fields on work orders. What are the possible status values available for these fields?
A. WMATL, AVAIL, NONE
B. COMP, NONE, PARTIAL
C. ONORDER, PAVAIL, READY
D. AVAIL. NOTAVAIL, PARTAVAIL
Answer: B

Which report option provides multiple access points for an end user to run reports including the tool bar shortcuts of Browser View, Direct Print. Direct Print with Attachments and direct access from application dialogs including Work Order Status Change and Inventory Reorder?
A. ERI BIRT
B. Cognos
C. SQL
D. Server
Answer: B

A company has assets at multiple locations that require maintenance There is a requirement to have a single work order with charges rolled up to a single GL account.
How can that be achieved?
A. Create a task work order for each asset
B. Create a child work order for each asset
C. Add a job plan that has the assets associated
D. Add the assets in Multiple Assets, Locations and Cis
Answer: B

An administrator has a requirement to create 44 new assets that each share a common configuration
Which application can do this with a single action?
A. Assets
B. item Master
C. Classifications
D. Asset Templates
Answer: D

A custom field has been added to the Work Order Tracking application to identify the inspector for environmental impacts of each work order. What type of role is used to assign the work order to the environmental inspector?
A. Person
B. Person Group
C. A set of data related to the record
D. A set of data related to the login user
Answer: A

What costing method should be used if the receipt cost of items that are the newest in stock is required?
A. LIFO
B. FIFO
C. Average
D. Standard
Answer: A

A vendor requires a payment of 20% of the purchase price when the purchase order (PO) is sent and the company wants to withhold of the payment until 90 days after receiving the item before final payment is made. How would this be accomplished'?
A. A Purchase Requisition would be created and three invoices would) be generated via the invoicing application One invoice tor 20%. one for 60% and one for 20%
B. A Price Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt.
C. A Blanket Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt
D. A Purchase Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt
Answer: D

A company has a requirement to report on actual labor hours, materials, services and tools used as work progresses on a work order.What is the earliest point in the basic life cycle a user can start reporting?
A.APPR
B. COMP
C. WMATL
D. WAPPR
Answer: A

An approved work order has been assigned an incorrect job plan. How do you correct this?
A. Change the Job Plan Revision to the correct revision
B. Clear the Job Plan field and enter the correct job plan
C. Create a Follow-up work order with the correct job plan.
D. Select Remove Work Plan from the More Actions menu and enter the correct job plan.
Answer: D

An administrator has a requirement to create 44 new assets that each share a common configuration Which application can do this with a single action?
A. Assets
B. item Master
C. Classifications
D. Asset Templates
Answer: D

A company has assets at multiple locations that require maintenance There is a requirement to have a single work order with charges rolled up to a single GL account.How can that be achieved?
A. Create a task work order for each asset
B. Create a child work order for each asset
C. Add a job plan that has the assets associated
D. Add the assets in Multiple Assets, Locations and Cis
Answer: B



CertTree IBM Maximo 7.6 C2010-555 questions and answers can not only help you save a lot of time. but also allows you to pass the exam successfully. So you have no reason not to choose it.CertTree IBM Maximo 7.6 C2010-555 questions and answers are made in accordance with the latest syllabus and the actual IBM C2010-555 certification exam. We constantly upgrade our IBM Maximo 7.6 C2010-555 questions and answers, all the products you get with one year of free updates. You can always extend the to update subscription time, so that you will get more time to fully prepare for the exam.

CertTree is a website to provide IT certification exam training tool for people who attend IT certification exam examinee. CertTree IBM Maximo 7.6 C2010-555 questions and answers has strong pertinence, which can help you save a lot of valuable time and energy to pass IT certification exam. Our IBM Maximo 7.6 C2010-555 questions and answers are very close true examination questions. IN a short time of using CertTree's simulation test, you can 100% pass the exam. So spending a small amount of time and money in exchange for such a good result is worthful. Please add CertTree IBM Maximo 7.6 C2010-555 questions and answers in your shopping cart now.